The Bazalgette Embankment I: images of work in progress

May 27, 2012. The site before Blackfriars Millennium Pier was moved.

A new public space close to Blackfriars Bridge, has been created by Tideway as part of their extensive work on London’s ‘Super Sewer’. I followed progress there on and off, somewhat randomly, and took photos as I passed over Blackfriars Bridge, or viewed the site from the opposite side of the river.

January 28, 2019. The cofferdam before completion, left open for a time to allow the removal of silt through the gap.

Co-ordinated work on the ‘Super Sewer’ began in 2016 “with activity taking place at two dozen construction sites from Acton in west London to Abbey Mills Pumping Station in Stratford, east London.”  Over the ten years that the project took to complete, nearly 4000 people with a wide range of skills were able to deliver the project with only a slight delay and increase in costs, caused by Covid. With allowances made for the massive disruption caused by the pandemic, the enterprise was seen by the press as “a masterclass in bringing a major infrastructure project in on time and within budget.”, APM.

View inside the cofferdam. ©Wal Daly-Smith, who was operating the Diveco safety boat for divers working below.

Wal Daly-Smith is just one of the several thousand workers employed by Tideway and has worked at several of the Tideway sites including at Blackfriars, where he was employed as a skipper responsible for crews working on maintenance and safety checks.

Eastern cofferdam completed.
The site on January 28, 2019 with workboat MERIDIAN and GPS tug CAMBRIA.
January 28, 2019. A complex variety of plant, tug MERIDIAN, and a GPS tug beyond.
February 15, 2019. In the mix, refuelling barges HEIKO and CONQUESTOR.
February 25, 2019. View from the Queen’s Walk on the South Bank.
February 25, 2019. A closer look from the Queen’s Walk, on the South Bank.
February 28, 2022View from Waterloo Bridge.
November 11, 2023, Uber Thames Clippers passing the floodlit site.
February 1st, 2024, RIVER PRINCESS and ONYX OF LONDON with the Bazalgette Embankment site in the background.
April 13, 2024. View from Blackfriars Bridge.
April 13, 2024. View of the site and the Blackfriars Bridges, from Victoria Embankment.
April 13, 2024. Closer view of the site.
April 13, 2024. Western cofferdam still in place.
April 6, 2026. Western part of the Bazalgette Embankment in place.
July 1, 2025, finishing touches.
April 30, 2026. The Bazalgette Embankment open to the public.
March 28, 2026. One of the many flowering shrubs planted on the Embankment.

In spring 2026, I first visited the Bazalgette Embankment with my husband and we enjoyed seeing the extensive and well conceived planting over this 1.5-acre space, which includes trees, flowering shrubs, grasses, plants and ferns giving a sense of calm in the heart of the city.

March 28, 2026. Restored Lion’s Head mooring ring.

The existing Lion’s Head mooring rings that lined the embankment at Blackfriars were carefully removed and restored, then replaced when work at the site was completed, as were the celebrated Vulliamy lampposts.

April 30, 2026. One of the restored Vulliamy lampposts at the top of the Embankment.
March 28, 2026. The view from one of the many benches on the Embankment.

The building of this new riverside space means that the northern part of the Thames Path has now become fully accessible and a pleasant place to walk or to run.

April 6, 2023. CITY DELTA, one of City Cruises’ sightseeing boats passing in front of the Bazalgette Embankment.
April 30, 2026. Photograph drawing attention to the momental work on the Tideway tunnel, 48 metres below, and paying homage to Sir Joseph Bazalgette.

Sir Joseph Bazalgette was Chief Engineer of The Metropolitan Board of Works, London’s civic authority. It was his talent, determination, and relentless energy that saw though the creation of London’s sewerage system after “The Great Stink” of 1858. It was a major undertaking, and a system that served London well for over a hundred years, until overflows and sheer quantity of raw sewage in recent years regularly ended up in the Thames. The answer: a new sewerage system on a massive scale. The construction of Tideway’s ‘Super Sewer’ was completed in 2024 and has been in service, fully connected, since 2025, now preventing pollution by diverting overflows through the 25 km tunnel into the treatment plant at Beckton.

April 20, 2026. View through the Blackfriars bridges from benches at the western end of the Embankment.

There are places to sit at several levels and care has been taken to make most of them wheelchair accessible. There is even space at the end of some benches “to allow wheelchair users to sit alongside.”

The clean granite paving, imaginative planting, striking sculptures, and views of river activity make the Bazalgette Embankment an interesting and pleasant place to pass the time.

In my next article I will focus on the artwork.

Note
London Rivers Week 2026 Launch Event at the Bazalgette Embankment, May 23rd, 2026: Standing by the Thames.

Sources and further information
The Bazalgette Embankment: Tideway, Opened to public, January 2026
Cofferdam construction: Tideway Update , September 2020
Cofferdam removal: Tideway Update, October 2022
London Centric: ‘London’s Newest Open Space’ Jim Waterson, January 21, 2026
The Thames Path National Trail

With the Flow

I

There are windless moments during slack tide when the Thames seems lake-still, perfectly mirroring trees and buildings on its surface but as you walk alongside, it’s the disturbance of tidal ebbs and flows that will catch your eye.

II
III
IV
V
VI
VII
VIII
IX
X
XI
XII

Notes
All pictures were taken along Lambeth Reach, mostly from Victoria Tower Gardens.
For tide times of the central London River Thames, see: BBC
There is a strong tidal flow along this stretch of the Thames, varying from 4 up to 8 knots.